A natural cost-effective solution for failing soil sports fields with minimal disturbance to the field. This is an environmentally sustainable approach versus artificial turf.
.jpg)
Drainage system installation
.jpg)
Laser-controlled trenching
.jpg)
Backfilling with sand
A drainage system is installed using laser-controlled trenchers at 6’-10’ spacings and backfilled with sand to the top. This allows excess surface water from the sand cap to enter the drain line.
.jpg)
Irrigation system upgrade
.jpg)
New stainless steel heads
.jpg)
Core aeration process
.jpg)
Aeration equipment
.jpg)
Removing cores
.jpg)
Planing the surface
.jpg)
Grading process
.jpg)
Seeding the field
.jpg)
Top dressing application
.jpg)
Final sand leveling
Top dressing sand is applied aggressively at 1/4" every 10-14 days until desired thickness is achieved.